2024 Ever Power Plant Generator Replacement
2024 Sun Ba Power Plant Generator Replacement
2024 Taichung Power Plant Unit 1 STG On-base Installation
2023 Da Tan Power Plant Unit 9 ST Installation
2023 Da Tan Power Plant Unit 8 Condenser Installation
2023 Hsinta Power Plant Unit 1 GT/GTG On-base
2021 Da Tan Power Plant Unit 8 STG On-base
2021 CSC No. 2 Converter Replacement
2020 CSC Blast Furnace Replacement
2019 Sun Ba Power Unit 2-1 Generator Replacement
2018 FENC Fiber Condenser Installation
2018 FENC Fiber Chimney Installation
2018 CCP MCG#5 Turbine、Generator and Condenser Installation
2018 TPRI Tongxiao Power Plant 2-3 Gas Turbine Dismantle
2018 EGAT No.4 Dock Hanger Installation
2018 TAMECO Hanger Doors Installation
2018 Sun Ba Power GTG-12 Inner Frame Renew and Transport
2017 Star Energy GTG-12 Inner Frame Renew and Transport
2017 Hai Hu EVER Power Generator-21 Replace
2016 TPC Tongxiao Power Plant Combined Cycle Unit 1、2、3 ST/STG,GT/GTG Condenser
Installation
2015 Long Chen Paper Er Lin PM7 Paper Mill Installation
2015 TPC Talin Power Plant #2 STG Erecting
2015 TPC Tongxiao Power Plant Unit 4 Combined Cycle Unit STG Renew
2014 TPC Talin Power Plant #1 STG Installation
2014 CCIP Star Energy GTG Renew
2014 BEC Linkou Power Plant Liner Cans Material Supply and Manufacturing / Installation
2013 FPCC Unit 3 HG2 Generator Renew
2013~2019 TPC Linkou Power Plant Unit 1~3 Boiler Installation
2013~2015 TPC Linkou Power Plant Unit 1&2 Condenser and Heater Installation
2012~2015 TPC Linkou Power Plant Unit 1&2 HP,HIP,ST/STG Installation
2011 Cheng Loong G3 STISTG Installation
2010 Cheng Loong 10M/C Paper Mill Installation
2009 BEC Panay Stack Liners
2009~2010 GPPC DA SHE Turbine and Generator Installation
2009 BEC Toledo Stack Liners Fabrication
2008 DRAGON STEEL Steam Turbine and Generator Installation
2007~2011 Long Men Nuclear Power Plant Unit 1&2 Condenser Installation
2006~2008 CPC Tao Yuan R-101 Dismantle and Renew
2006~2009 Da Tan Power Plant Unit 3/4/5/6 Condenser Installation
2006~2008 Da Tan Power Plant Unit 3/4/5/6 Steam Turbine and Generator Lifting
2006 Da Tan Power Plant Unit 3/4/5/6Stack and HRSG Boiler Modules Lifting
2006 CPC No.26 Generator Lifting
2005~2006 Da Tan Power Plant Unit 1&2 Condenser Installation
2004~2006 Da Tan Power Plant HRSG Boiler and Stack Installation
2004~2005 Da Tan Power Plant GTG、STG、BSGT Installation
2003~2007 Long Men Nuclear Power Plant Unit 1&2 Condenser Fabrication
2002~2003 NAN BU Power Plant HRSG Boiler Module Lifting
2001 Hsin Tao Power Plant Steam Turbine and Steam Generator Installation
2000~2003 Ho-Ping Power Plant Condenser Construction、Steam Turbine Lifting
2000~2001 CPC Zuoying Unit 23&24 Condenser Construction
1999 VEDAN Vietnam Steam Turbine and Generator Lifting and Adjustment
1998~1999 Tongxiao Power Plant HRSG Boiler Module Lifting
1998~1999 REN WU Incinerator Stack、ACC、T/G Fabrication and Installation
1998~1999 NAN QU Incinerator Stack、ACC、T/G Fabrication and Installation
1997~1999 FPG Mailiao Condenser Unit 2&3 Construction
1996~1998 XIN DA Power Plant HRSG Boiler Module Lifting
1996 CLC No.7 Paper Machine Installation and Piping
1995 CAPC No.5 Tower、Tank and Piping
1994 NAN BU Power Plant HRSG Boiler Module Lifting
1992 CPC Naphtha Cracker Section V Cracking Furnace Piping
1990 CLC No.9 Paper Mill Piping Installation
1989~1991 CAPP No.3&4 Silo Tower and Piping
1987 CLC No,1&2 Paper Mill Piping Installation
1986 CSC Construction of Steel Structure and Equipment Installation
1985 CLC No.8 Paper Mill Piping Installation
1984 CAPC No.2 Chemical Plant Tower 、Tank and Piping Installation
1983 CSC LPG Tank Installation
1981 CPC No.1 RDS Piping
1979 CPC Naphtha Cracker Section IV Cracking Furnace Construction